Beryl Solar Farm Sold To New Energy Solar

We’ve written about the Beryl Solar Farm reaching a financial close back in May – now the 87MW (108MW according to the AFR) project has a new owner and is continuing construction. 

Beryl Solar Farm Sold To New Energy Solar

Beryl Solar Farm Sold to New Energy Solar
Beryl Solar Farm Sold to New Energy Solar (source: FirstSolar.com.au)

According to PV Magazine, the farm has been purchased by New Energy Solar – who also bought the 50MW Manildra Solar Farm for $113m last month. Both farms were previously owned by First Solar and the Beryl farm will be using their 420W large-format Series 6 thin film PV modules. Beryl also comes with a 15 year PPA with Transport for NSW – who will purchase 134,000 MWh from Beryl Solar Farm each year – using the power for the Sydney Metro Northwest railway. This long PPA with a AAA rated customer (i.e. the government) makes the farm a great buy in its current shape.

The EPC project was estimated at $150m according to Reuters, but it’s now estimated at $187m. Downer Utilities started work on the project in May and hope to have it finished in mid 2019. The farm will produce enough energy to power 25,000 households and doesn’t require any water for its electricity generation.

New Energy Solar said the cost of the farm won’t be announced but it was pegged to a target for five-year annual average gross yield of 8.2%, in comparison with yield on its existing portfolio of about 6.8% p.a, so by those metrics it looks like a canny purchase. 

New Energy Solar’s CEO, John Martin, discussed how the extra-long 15 year PPA helped get the sale of this project over the line:

“Beryl, New’s second investment in Australia, will further enhance the scale and contracted cashflows of our Australian portfolio,” said Martin. “Following the Manildra acquisition last month, we are delighted to be consolidating our relationship with First Solar through this second sizeable transaction in the Australian market.”

Martin continued to say that ~69% of the energy provided by the Beryl project will go to Transport for NSW – with the rest slated to package up with a 20MWh battery and sold to a corporate customer as commercial solar

To learn more about the project from the First Solar website please click here

If you’re interested in solar employment and working at the Beryl Solar Farm, please click here to visit the Downer Group’s careers website.

Read More Solar News:

Beryl Solar Farm reaches financial close.

First Solar have reached a financial close at the 87MW Beryl solar farm in New South Wales. The farm will be one of the world’s first to use First Solar’s Series 6 modules (with 420+ watts per module) and will be constructed by Downer EDI. 

Beryl Solar Farm – Construction and Financial Close

Beryl Solar Farm
Beryl Solar Farm (site: firstsolar.com.au)

Beryl is around five km from Gulgong in central west NSW. This is one of NSW’s biggest completed solar farms but there are some upcoming projects which will dwarf it (such as the 200MW Sunraysia solar farm in Balranald or the $380m Gunning Solar Farm – with solar there are always bigger plans in place!).

According to a press release on Reuters, the engineering, procurement and construction (EPC) contract is worth about $150m and construction will commence soon.

TransGrid’s head of business growth Richard Lowe discussed how they will be able to integrate into the project: “The project is located approximately 250 metres south of TransGrid’s Beryl Substation, so we have been able to offer a very competitive and attractive asset connection plan to First Solar,” Lowe said in a statement on the TransGrid website.

“The Beryl Solar Farm will connect directly into TransGrid’s high-voltage electricity transmission network via a 66kV connection to a new bay at Beryl Substation.

“This connection will allow the export of 87 megawatts of power into the National Electricity Market – enough to serve the needs of approximately 25,000 average NSW homes, while the associated carbon emission displacement is equivalent to taking about 45,000 cars off the road.” the statement from TransGrid continued.

TransGrid will oversee the construction and operation of a new substation at the Beryl solar farm so they’re able to then connect that to the existing Beryl substation. This will happen in the second half of the year. 

If you’d like to learn more about the Series 6 module please click here to watch a video on the manufacturing process. 

Read More Solar News: